Abandoned Railroad Lines: Reversion, Railbanking, and Liability

Ownership of an abandoned railroad line depends on two questions: how the railroad originally acquired the corridor, and whether the Surface Transportation Board has formally authorized abandonment. Where the railroad held only an easement, the land reverts to whoever owns the adjacent property once abandonment is complete. Where the railroad held fee simple title, it owns the ground outright and can sell it. And where the corridor has been “railbanked” for possible future rail use, the land does not revert at all, even though the tracks are gone.

When a Line Is Actually Abandoned

A rusted rail and a decade of silence do not add up to legal abandonment. A rail carrier that wants to abandon a line must file an application with the Surface Transportation Board, and the Board authorizes abandonment only if it finds that public convenience and necessity permit it.1Office of the Law Revision Counsel. 49 USC 10903

Even after the Board grants permission, the railroad is not finished. It must file a notice of consummation within one year confirming that abandonment has actually been carried out. If the railroad fails to file that notice and no legal barriers exist, the abandonment authority expires automatically, and the carrier would have to start over.2eCFR. 49 CFR Part 1152 – Abandonment and Discontinuance of Rail Lines and Rail Transportation Under 49 USC 10903 That is why a corridor can sit idle for years without ever being legally abandoned. Until the paperwork is complete, the line remains under federal jurisdiction and the railroad’s interest in the land continues.

Who Gets the Land: Fee Simple vs. Easement

Once abandonment is legally complete, the ownership question turns on the original deed. Many corridors are a patchwork, with the ownership type shifting mile by mile depending on how each parcel was acquired.

Where a railroad holds fee simple title, it owns the land outright and can sell it after the Board authorizes abandonment.2eCFR. 49 CFR Part 1152 – Abandonment and Discontinuance of Rail Lines and Rail Transportation Under 49 USC 10903 Fee simple is common where a railroad bought land directly from private sellers or developers.

An easement is different. It gives the railroad a limited right to use the land for railroad purposes only, while underlying ownership stays with the original grantor or their successors. When a railroad operating under an easement permanently abandons the corridor, the easement terminates and the land reverts to the underlying owner, free of any railroad interest. Courts read the original deed closely. Phrases like “for railroad purposes only” or “so long as used for a railroad” are strong indicators that only an easement was granted and that reversionary rights exist.

Adjacent landowners frequently discover that their property lines technically extend to the centerline of the old tracks. Proving it, however, requires digging through deeds that may be more than a century old, and disputes over the wording of those grants generate serious title litigation.

Federal Land Grants Follow Different Rules

A large share of the nation’s rail network was built across public land under federal grants, and the era of the grant controls what the railroad actually received.

The major transcontinental grants before 1871, including the Pacific Railroad Acts of 1862 and 1864, gave railroads a “limited fee” in the right-of-way. That interest reverts to the federal government, not to adjacent landowners, if the railroad stops using the corridor.

After 1875, Congress changed course. The General Railroad Right-of-Way Act of 1875 granted railroads only an easement across public lands, extending 100 feet on each side of the central line, plus limited acreage for stations.3Office of the Law Revision Counsel. 43 USC 934 The Supreme Court confirmed in Great Northern Railway Co. v. United States that this language created a surface easement, not a strip of fee-simple land.

The practical consequence hit home in 2014 with Marvin M. Brandt Revocable Trust v. United States. The Court held that when a railroad abandons a right-of-way granted under the 1875 Act, the easement disappears and the underlying landowner’s title becomes “unburdened” by the former railroad interest.4Justia US Supreme Court. Marvin M. Brandt Revocable Trust v. United States, 572 US 93 (2014) The federal government had argued it kept ownership of the abandoned corridor. The Court disagreed: the land belonged to the private landowner whose patent had always been subject to the railroad easement.

The dividing line matters. If a corridor was built under a pre-1871 grant, the federal government may have a reversion claim. If it was built under the 1875 Act, the adjacent landowner whose chain of title traces back to the original land patent is the one who benefits from abandonment.

Railbanking Freezes Reversion

A corridor can also be preserved through a process called railbanking. Under the National Trails System Act, a railroad facing abandonment can transfer its corridor to a qualified trail sponsor for interim recreational use.5Office of the Law Revision Counsel. 16 USC 1247 – State and Local Area Recreation and Historic Trails The statute treats the corridor, “for purposes of any law or rule of law,” as not abandoned for railroad purposes. That single provision keeps the corridor intact and blocks adjacent landowners from reclaiming the underlying land, even after the rails come out.

The trail sponsor, which can be a state, local government, or qualified private organization, takes on management of the corridor, legal liability from trail use, and property taxes.5Office of the Law Revision Counsel. 16 USC 1247 – State and Local Area Recreation and Historic Trails The corridor remains available for possible future reactivation as a rail line.

Compensation When Railbanking Blocks Your Reversion

Railbanking creates real friction with property rights. When a corridor held as an easement is railbanked instead of abandoned, the adjacent landowner’s reversionary interest is prevented from vesting. Under normal state property law the easement would end and the land would come back. The National Trails System Act stops that by declaring the corridor “not abandoned.”

The Supreme Court addressed this tension in Preseault v. ICC, noting that interim trail use will “inevitably conflict with the reversionary rights of adjacent land owners” and that blocking those rights is “the very purpose of the Trails Act.” The Court did not strike railbanking down. Instead, it held that if the government’s action amounts to a taking of the landowner’s reversionary interest, the Fifth Amendment requires just compensation, recoverable in the U.S. Court of Federal Claims under the Tucker Act.6Legal Information Institute (Cornell Law School). Preseault v. Interstate Commerce Commission, 494 US 1 (1990)

What You Have To Show

To win a takings case, a landowner generally must show four things: they owned land adjacent to the corridor, the railroad held the corridor as an easement rather than in fee simple, the Board issued a Notice of Interim Trail Use (NITU) or Certificate of Interim Trail Use (CITU), and a trail-use agreement was reached.

The court then applies a “before-and-after” measure. It values the property as if the easement had terminated normally, subtracts the value of the property burdened by the recreational trail easement, and awards the difference.

The Six-Year Deadline

Landowners have six years to file a takings claim in the Court of Federal Claims.7Office of the Law Revision Counsel. 28 USC 2501 The clock starts when the Board issues its first railbanking order, the NITU or CITU, not when a trail-use agreement is finalized or the trail opens. Miss it and the claim is barred permanently. A landowner who only discovers years later that a reversionary interest was blocked has no recourse if six years have already run.

Environmental Liability Can Come With the Land

Owning a reverted railroad corridor is not automatically a windfall. Decades of railroad operations leave behind hazardous materials: railroad ties treated with creosote, coal ash containing lead and arsenic, spilled fuel and solvents, and herbicides used to control trackside vegetation. These contaminants leach into soil and groundwater.

Under the Comprehensive Environmental Response, Compensation, and Liability Act, current owners of contaminated property can be held responsible for cleanup, even if they had nothing to do with the original contamination. The statute reaches current owners and operators, past owners and operators at the time hazardous substances were disposed, and anyone who arranged for disposal.8Office of the Law Revision Counsel. 42 USC 9607 Liability is joint and several, so a single party can be held responsible for the entire cost of remediation unless it can prove a reasonable basis for splitting the bill.

If a corridor reverts to you after abandonment, cleanup responsibility for contamination a railroad created a century ago can come with it. Anyone considering acquiring or developing former railroad land should get an environmental site assessment before closing.

Adverse Possession Won’t Get You There

Neighbors who have been mowing, fencing, or otherwise using part of an active or federally granted railroad right-of-way cannot claim that land through adverse possession. The Supreme Court established long ago that railroad rights-of-way granted by Congress serve a public purpose and cannot be acquired through occupation over time, no matter how long.9Legal Information Institute (Cornell Law School). Union Pacific Railroad Company v. Laramie Stock Yards Company While the corridor remains under federal jurisdiction or the railroad holds a valid interest, squatter’s rights are off the table.

Verifying a Corridor’s Legal Status

Before treating an idle line as available land, confirm its status. The Surface Transportation Board’s electronic filing system is the starting point. You can search dockets by railroad name or location and find whether a certificate of abandonment was issued, whether a trail-use agreement is in effect, or whether the line is simply out of service.2eCFR. 49 CFR Part 1152 – Abandonment and Discontinuance of Rail Lines and Rail Transportation Under 49 USC 10903

County land records provide the next layer: the original deeds, any recorded transfers, and plat maps showing the right-of-way boundaries. Historical railroad valuation maps, detailed surveys the government once required railroads to maintain, can help clarify the original width and nature of the corridor.10Federal Transit Administration. Valuation of Railroad Right of Way

For anything beyond a basic status check, a title examiner or attorney who works with railroad property is close to essential. The deed chains often stretch back more than a century, pass through multiple corporate successors from railroad mergers and reorganizations, and mix federal grants, state grants, private purchases, and condemnation proceedings within the same corridor. A proper title search reveals whether the railroad held fee simple or an easement, whether reversion clauses exist, and whether any environmental liens encumber the property. That work is inexpensive compared to developing land you do not actually own or inheriting a contamination bill you did not see coming.