Commencement of work, for purposes of a notice of commencement and lien priority, is the moment physical construction activity first changes the property. Signing a contract does not start the clock. Pulling a permit does not start the clock. Breaking ground, demolishing a structure, clearing trees, grading soil, or delivering materials that will become part of the improvement does. That date matters because in many states every mechanics lien filed on the project relates back to it, and a lien that relates back can jump ahead of a mortgage recorded later. Getting the date and the paperwork right is what keeps a lender in first position and an owner from paying for the same work twice.
What Counts as Commencement
Courts look for permanent, visible changes tied to the planned improvement. A contractor driving the first stakes for a building footprint has commenced work. A surveyor walking the property with a measuring wheel probably has not. The test in most jurisdictions is whether the activity is a permanent part of the overall improvement and visible enough that a reasonable observer would recognize a construction project has started.
Preconstruction tasks generally sit on the safe side of the line. Planning, surveying, setting property lines, obtaining soil samples, and drafting architectural plans are usually not treated as commencement for lien purposes. They are necessary, but they do not physically alter the land in a way that puts the world on notice.
Borderline activities generate regular litigation. Delivering specialized equipment, installing a construction fence, or setting up a job-site trailer may or may not qualify depending on the jurisdiction and the facts. Mowing grass or a basic walkthrough almost never counts. If you are a lender or owner trying to pin down the exact date, treat the earliest physical activity as commencement.
Why the Commencement Date Drives Lien Priority
The commencement date gets its power from the relation-back doctrine. In many states, every valid mechanics lien recorded during or after the project relates back to the date physical work first began on the property. A plumber who finishes work in month eight and files a lien in month nine is treated, for priority purposes, as though that lien existed from day one of construction.
Under relation-back, a mechanics lien can jump ahead of a mortgage recorded after the commencement date, even if the lien was filed months later. The logic: labor and materials that physically created the improvement should not be subordinated to a loan recorded after the project was already underway. Florida, Texas, Idaho, and Colorado follow some version of this approach.
Not every state works this way. Some tie lien priority to the date the individual claimant first furnished labor or materials. Others treat mechanics liens as subordinate to any previously recorded mortgage. The distinction determines who gets paid first if the project fails and the property is sold or foreclosed.
The Notice of Commencement
A notice of commencement is a recorded document that formally announces the start of a construction project and identifies the key parties. Not every state requires one. Florida, Georgia, Michigan, Iowa, and Nebraska are among the states with statutory notice-of-commencement requirements. Many states have no such filing obligation, though the underlying commencement date still drives lien priority regardless.
Where the notice is required, it must typically be recorded before physical work begins. It creates a clear public record of the project’s start date and gives subcontractors and material suppliers the information they need to protect their own lien rights. Failing to record one before work starts can expose the owner to serious financial consequences later.
Information the Notice Must Contain
The specific contents vary by state, but most statutes require the same core information:
- Full legal name and address of the property owner, plus the fee simple titleholder’s name if different from the owner contracting for the work.
- Legal description of the property from the deed, not just a street address, meaning lot and block or a metes-and-bounds description that uniquely identifies the parcel in public records.
- General contractor’s business name, address, and license or registration number.
- Construction lender’s name and contact information, if a construction loan is involved.
- Tax parcel number, matching official records exactly.
- Brief description of the improvement, such as “new single-family residence” or “commercial tenant buildout.”
In some states, a lessee who contracts for improvements to leased property is treated as the “owner” for notice purposes. The lessee must be listed as owner on the notice, with a statement that the ownership interest is a leasehold. This matters for tenant improvement projects where the landlord is not the contracting party.
The owner or an authorized agent must sign, and most states require notarization. The notary must complete a full acknowledgment, including the signer’s name and the type of authority they hold when signing on behalf of an entity. A missing or incomplete notarization is one of the most common reasons a notice gets rejected at the recorder’s office.
Recording and Posting the Notice
Recording means submitting the completed, notarized document to the county clerk or recorder of deeds where the property is located. Most offices accept in-person filings, and many now offer electronic recording. Fees vary widely: expect roughly $5 to $70 for a standard one-page document, with additional per-page charges for longer notices or certified copies.
Get a stamped or certified copy once the document is recorded. That copy is your proof of public record and belongs in the project’s permanent file. Many states also require the owner to post a copy at the job site in a visible location such as the permit board. Posting puts subcontractors and suppliers on notice of the project details and their lien rights. In some jurisdictions, the building department will not perform inspections until a copy of the recorded notice has been submitted.
Timing is the point of the whole exercise. The notice must be recorded before physical work begins. If a contractor breaks ground before the notice is on file, the owner may lose the procedural protections the notice provides. Some states also treat the notice as void if actual construction does not start within a set window after recording. In Florida, a notice of commencement becomes void if the improvement described does not actually begin within 90 days of recording.
Keeping the Notice Alive
A notice of commencement does not last forever. It typically has a built-in expiration period, with a common default of one year from recording. If the construction contract calls for a longer completion period, the notice must state that extended timeframe, or the owner needs to amend the notice before it expires.
Letting a notice expire mid-project is a costly mistake. Payments made after expiration may be treated as “improper payments” that do not discharge the owner’s liability to unpaid subcontractors or suppliers. Paying the general contractor for work done after the notice expired could leave the owner on the hook to pay again if a subcontractor files a lien. If the project will run past the original expiration date, record an amendment extending the effective period before the deadline passes.
A notice can also be amended to correct errors or add omitted information. Changing the general contractor named on the notice, however, typically requires recording a new notice of commencement rather than a simple amendment.
How Lenders Protect Their Priority
Construction lenders understand relation-back and plan around it. The most common tool is the no-work affidavit, sometimes called a no-lien affidavit. Before a construction loan closes, the lender sends an inspector to the property to verify that no construction activity has occurred and no materials have been delivered. The owner then signs a sworn statement confirming that no work has commenced.
The no-work affidavit is recorded just ahead of the construction mortgage. That sequence establishes the mortgage was in place before any lien-triggering activity began, protecting the lender’s first-priority position. If work started even one day before the mortgage recording, any subsequent mechanics lien could potentially prime the mortgage under relation-back. A lender who discovers evidence of prior work at the site inspection will typically refuse to close until the situation is resolved.
Throughout the project, lenders also rely on lien waivers collected with each draw request. Before releasing funds for each phase, the lender requires signed waivers from the general contractor and major subcontractors confirming they have been paid for prior work. This ongoing monitoring is the lender’s primary defense against accumulating lien claims that could erode its security interest.
Title insurance shapes the same problem from the other side. When work begins before the mortgage is recorded, title professionals call it “broken priority.” If a title company discovers construction has commenced before the proposed mortgage recording date, it may refuse to insure the lender’s priority position without adding an exception for mechanics liens. Some insurers offer “early start” or “unrestricted lien coverage” with conditions attached: loan proceeds may have to be disbursed directly to subcontractors rather than to the borrower, lien waivers collected at every stage, and pending disbursement endorsements added to the policy to limit exposure.
How Owners Avoid Paying Twice
The most painful consequence of getting commencement wrong falls on owners who end up paying twice for the same work. The pattern is common: the owner pays the general contractor, the general contractor fails to pay a subcontractor, and the subcontractor files a mechanics lien against the property. If the owner did not follow proper payment procedures, the money already paid to the general contractor does not count as satisfaction of the subcontractor’s claim, and the owner now owes the subcontractor directly.
A properly recorded notice of commencement creates the framework for “proper payments.” When the notice is on file and the owner follows statutory payment procedures, the owner builds a defense against double-payment claims. Without the notice, or after it expires, payments to the general contractor may not be recognized as discharging obligations to downstream parties.
Several practical steps reduce exposure beyond filing the notice:
- Track preliminary notices. In many states, subcontractors and suppliers must send the owner a preliminary notice within a set period after first furnishing labor or materials. Keep a log of every notice received.
- Collect lien waivers with every payment. Before paying the general contractor for each phase, require signed conditional lien waivers from every subcontractor and supplier who sent a preliminary notice.
- Use joint checks. Once you know which subcontractors have lien rights, write checks payable to both the general contractor and the subcontractor, so the subcontractor must endorse the check to get paid.
- Hold retention. Withhold a percentage of each payment, typically around ten percent, until all liens are released at the end of the project.
- Record a notice of completion. Recording one at the end of the project shortens the window during which new liens can be filed.
Closing Out the Notice
Once construction is complete and all parties have been paid, the notice of commencement needs to be formally closed. In states that require the notice, this means recording a notice of termination. The termination document must reference the original notice by its recording information, state the termination date, and include a statement that all lienors have been paid in full.
The owner must serve a copy of the termination on the general contractor and on every subcontractor or supplier who either has a direct contract with the owner or who previously sent a notice to owner. The termination does not take effect immediately upon recording. A common rule is that it becomes effective 30 days after recording or on the date stated in the notice, whichever is later.
Skipping the termination leaves an open-ended record in the public files. A future title search will reveal an active construction notice with no corresponding termination, which can complicate a sale or refinance. Clean project closeout means recording the termination, confirming all waivers are in hand, and keeping copies of everything in the permanent file.