Commercial Operation Date: Requirements, Filing, and Financial Impact

A project’s commercial operation date, or COD, is the day a power facility stops being a construction site and starts being a revenue-generating asset able to deliver electricity to the grid under its power purchase agreement. It is a contractual milestone, not a ribbon-cutting: the plant has to prove it works, prove it has permission to operate, and give the buyer formal written notice before the date is official. Everything that follows in the project’s financial life — the PPA revenue clock, debt conversion, insurance, tax positions, reporting — pivots on this one date.

How the Industry Defines Commercial Operation

The Federal Energy Regulatory Commission’s pro forma Large Generator Interconnection Agreement defines commercial operation as “the status of a Generating Facility that has commenced generating electricity for sale, excluding electricity generated during Trial Operation.”1Federal Energy Regulatory Commission. Pro Forma Large Generator Interconnection Agreement That distinction between trial power and commercial power is doing real work. Electricity generated during testing does not count toward PPA obligations and usually earns a lower rate or no revenue at all. COD is the line between the two.

Most PPAs layer their own conditions on top of the FERC definition. A typical agreement requires the facility to pass performance tests, obtain all necessary permits, execute a final interconnection agreement, and deliver a formal notice to the off-taker before the date becomes official. Specifics vary contract to contract, but the core idea is consistent: prove it works, prove it is allowed to run, and notify the buyer in writing.

Physical and Operational Requirements

Before a facility can claim commercial operation, it has to perform to its design specifications under real conditions. That means running at or near nameplate capacity for a sustained period. The duration depends on the contract and the technology, but full-load tests lasting anywhere from a few hours to several days are standard. The point is to confirm the plant can hit the megawatt-hour targets in the engineering plans without recurring mechanical failures or safety shutdowns.

The facility also has to synchronize with the regional grid. In the United States, that means matching the grid’s 60 hertz frequency precisely, which requires protective relays, circuit breakers, and supervisory control and data acquisition (SCADA) systems so the utility can monitor flow and respond to faults in real time.1Federal Energy Regulatory Commission. Pro Forma Large Generator Interconnection Agreement The interconnection customer installs and maintains system protection on its side of the connection; the transmission provider installs any additional protection needed on its side, at the customer’s expense.

Only after the facility can send power through a permanent interconnection point, and has shown it can do so reliably, is it operationally ready.

Documentation and Verification

Meeting the physical standards is half the job. The other half is a paper trail. Most PPAs require an independent engineer’s report confirming the facility was built to specification and is safe for continuous operation. Some agreements make the report mandatory; others require it only if the buyer asks. Either way, it functions as third-party confirmation that the project is ready.

The package also includes the executed interconnection agreement, which is the facility’s legal authority to remain connected and transmit energy. FERC’s standard agreement requires the transmission provider to file it with the appropriate governmental authority when required.1Federal Energy Regulatory Commission. Pro Forma Large Generator Interconnection Agreement Smaller projects that fall under state jurisdiction rather than FERC’s follow the local utility’s tariff rules for interconnection.2Federal Energy Regulatory Commission. Generator Interconnection

The last piece is the performance testing data: peak output, efficiency ratings, and any reliability metrics the PPA calls for. Assembling all of it into one verified package before filing the notice heads off the kind of administrative rejections that can push COD back by weeks.

Filing the Notice of Commercial Operation

The notice has to follow the exact delivery method the PPA specifies. Most agreements require certified mail with return receipt, a recognized overnight courier, or a secure electronic portal the utility maintains. The delivery method matters because the notice creates a verifiable record of when the declaration reached the off-taker, and that timestamp can affect revenue start dates and liquidated damages calculations.

Timing is tight. PPAs typically require the notice within a specific window after the physical and documentation milestones are met. After submission, the off-taker has a defined review period. It may countersign or issue a formal acknowledgment. If it finds discrepancies, it can issue a dispute notice that has to be resolved before COD is finalized. Close communication through this window is what keeps the official date from slipping.

How COD Relates to the “Placed in Service” Date

The IRS does not use the term “commercial operation date.” It uses “placed in service,” and the two overlap but are not identical. Under IRS regulations, energy property is placed in service in the earlier of the year depreciation begins or the year the property is “in a condition or state of readiness and availability for a specifically assigned function.”3eCFR. 26 CFR 1.48-9 – Definition of Energy Property A facility can satisfy the IRS placed-in-service test before the contractual COD is declared, or after, depending on how the contract defines its milestones.

The gap matters because placed-in-service, not COD, is what governs eligibility and start dates for federal clean energy tax credits under Sections 45Y and 48E, MACRS cost recovery, and any first-year bonus depreciation under Section 168(k).5Office of the Law Revision Counsel. 26 USC 168 – Accelerated Cost Recovery System

What Changes Financially at COD

COD is when the project starts making money. The revenue-generating term under the PPA begins, and the owner can bill the off-taker for delivered energy at the contracted rate. That cash flow is what services debt and pays equity investors. Before COD, the project burns cash. After it, the project generates cash.

In most project finance structures, the construction loan converts to a long-term loan at COD. The term loan typically carries a lower interest rate, which improves cash flow. Lenders require evidence of COD, including the independent engineer’s report and the executed notice, before they release construction-phase reserves and finalize the conversion. A delayed COD means extended time on a higher-rate construction loan, which cuts into project economics.

Insurance shifts, too. During construction, the project carries builder’s risk policies. At COD, the facility transitions to operational all-risk coverage for fire, natural disasters, vandalism, and mechanical defects, plus the labor and transport costs of repairs. The operational policy usually includes business interruption coverage that compensates the owner for lost revenue during covered outages, typically for six to twelve months. Insurers often require a post-commissioning inspection before binding the operational policy.

Liquidated Damages and the Longstop Date

Most PPAs and engineering, procurement, and construction (EPC) contracts include liquidated damages provisions that penalize the project owner or contractor for each day COD is delayed past the target date. The daily rate varies widely with project size, contract value, and negotiating leverage, and it is meant to approximate the buyer’s actual losses from the delay. Once the facility reaches commercial operation, the damages stop accruing. That creates intense financial pressure to hit the target.

Beyond daily penalties, a project that misses COD by enough can trigger the off-taker’s right to terminate the PPA. Most agreements include a “longstop date” or “guaranteed COD” that functions as the outer deadline. If the project is not operational by then, the buyer can walk away. Losing the PPA does more than eliminate revenue; it can collapse the financing structure, because lenders underwrote their loans against that contracted cash flow.

Reporting Obligations That Begin at COD

Reaching commercial operation triggers federal reporting duties. Any power plant with a total generator nameplate capacity of 1 megawatt or greater that is connected to the grid must file Form EIA-860 with the U.S. Energy Information Administration. The form requires the month and year the generator began commercial operation, and it is submitted annually between the first business day of January and the last business day of February, reflecting the facility’s status as of December 31.
4U.S. Energy Information Administration. Form EIA-860 Instructions – Annual Electric Generator Report First-time filers and facilities that take actions not previously reported are expected to notify the EIA as soon as practical.

Larger facilities, particularly steam-electric plants of 10 megawatts and above, also submit monthly generation data through Form EIA-923.6U.S. Energy Information Administration. Form EIA-923 Detailed Data These reporting obligations begin at COD and continue for the life of the facility, so it is worth building the reporting cadence into operational procedures from day one.