Cost Plus Fixed Fee Contract: Costs, Fee, and Ceiling Rules

A cost-plus-fixed-fee contract, often shortened to CPFF, reimburses a contractor for the allowable costs of doing the work and pays a separate profit amount that was locked in before performance began. The fee does not move when actual costs move. Federal agencies use this structure for research, development, and other projects where nobody can credibly estimate the final price at the outset, which is why most of the cost risk sits with the government rather than the contractor.

The Two Payments Inside the Contract

A CPFF deal has two financial pieces working side by side. The government reimburses the contractor’s actual, allowable expenses as the work progresses. Separately, it pays the fixed fee that both sides negotiated up front. That fee holds steady whether costs come in high or low. It can be adjusted only if the scope of work formally changes through a contract modification.

The fixed part matters because of what it isn’t. In a cost-plus-percentage-of-cost arrangement, the contractor’s profit grows automatically as spending grows, which rewards overruns. Federal law prohibits that structure in government procurement.1GovInfo. 41 USC 3905 – Cost Contracts A fixed fee cuts the link. If the contractor overspends, profit stays flat and the effective margin shrinks; if the contractor controls costs, the margin improves.

When Agencies Use a CPFF Contract

Contracting officers are supposed to reach for cost-reimbursement contracts only when the work genuinely cannot support a fixed price. The Federal Acquisition Regulation allows them in two situations: when the agency’s requirements can’t be defined precisely enough for a fixed-price contract, or when uncertainties in performance make it impossible to estimate costs accurately enough to use one.2Acquisition.GOV. Federal Acquisition Regulation 16.301-2 – Application Early-stage research, prototype work, and novel engineering programs are the textbook fits.

There is one boundary worth flagging. On major defense systems, once preliminary studies and risk reduction show that development is likely achievable and the government has firm performance objectives, a CPFF contract normally should not be used.3Acquisition.GOV. Federal Acquisition Regulation 16.306 – Cost-Plus-Fixed-Fee Contracts At that stage the program is expected to move to a fixed-price or incentive contract.

Completion Form and Term Form

Not every CPFF contract earns its fee the same way. The FAR recognizes two forms, and the difference decides what the contractor has to deliver to collect.

Completion Form

A completion-form contract defines a specific end product or goal. The contractor earns the entire fixed fee by delivering that product within the estimated cost. If the work can’t be finished within budget, the government can require the contractor to keep going without any increase in fee, provided the government raises the estimated cost to cover continued performance.3Acquisition.GOV. Federal Acquisition Regulation 16.306 – Cost-Plus-Fixed-Fee Contracts On a completion-form deal, a contractor can end up doing more work for the same profit if the project runs long.

Term Form

A term-form contract defines the work in general terms and requires the contractor to devote a specified level of effort over a set time period. The fixed fee becomes payable at the end of that period if the government considers performance satisfactory and the contractor certifies it expended the agreed effort.3Acquisition.GOV. Federal Acquisition Regulation 16.306 – Cost-Plus-Fixed-Fee Contracts Renewing a term-form contract for another period is treated as an entirely new acquisition with fresh cost and fee negotiations.

The government prefers the completion form when the work is defined clearly enough to build cost estimates around, because it puts a stronger obligation on the contractor to finish the job.3Acquisition.GOV. Federal Acquisition Regulation 16.306 – Cost-Plus-Fixed-Fee Contracts The term form is reserved for work where even the deliverable can’t be pinned down.

Which Costs Get Reimbursed

Because the government is picking up the tab for actual expenses, strict rules govern what counts. Under FAR Part 31, a cost is allowable only when it meets five conditions: it must be reasonable, allocable to the contract, consistent with cost-accounting standards or generally accepted accounting principles, permitted by the contract’s terms, and not barred by a regulatory limitation.4Acquisition.GOV. 48 CFR 31.201-2 – Determining Allowability

Costs sort into two families. Direct costs are tied straight to the contract work: labor hours on the project, raw materials, equipment used for it. Indirect costs benefit multiple projects and get spread through predetermined rates. Overhead (facilities, utilities, management salaries) and general-and-administrative expenses are the common pools.

Some categories are unallowable regardless of how reasonable they look:

How Large the Fee Can Be, and How It Gets Paid

Federal statute caps the fixed fee, and the ceiling depends on the work. For experimental, developmental, or research contracts, the fee cannot exceed 15 percent of the estimated cost, excluding the fee itself. For architect-engineer services on public works, the combined contract price cannot exceed 6 percent of the estimated construction cost. For all other CPFF contracts, the cap is 10 percent.8Office of the Law Revision Counsel. 10 USC 3322 – Cost Contracts These are ceilings, not targets. The actual fee is negotiated based on complexity, risk, and level of effort.9Acquisition.GOV. 48 CFR 15.404-4 – Profit

The fee is paid incrementally as work progresses, but the government withholds a reserve. That reserve cannot exceed 15 percent of the total fixed fee or $100,000, whichever is less. After the contractor submits an adequate certified final indirect cost rate proposal for the year the work was physically completed, the contracting officer releases 75 percent of what was withheld. A contractor with a strong track record on settling indirect cost rates can see up to 90 percent released.10Acquisition.GOV. FAR 52.216-8 – Fixed Fee

The Cost Ceiling and the Notification Rule

The estimated cost in a CPFF contract is more than a forecast. It functions as a funding ceiling. The government has no obligation to reimburse anything beyond the estimated cost in the contract schedule, and the contractor has no obligation to keep working past that point unless the contracting officer formally increases the estimate in writing.11Acquisition.GOV. FAR 52.232-20 – Limitation of Cost

Contractors also carry an early-warning duty. When the contractor expects costs in the next 60 days, added to costs already incurred, to exceed 75 percent of the estimated cost, it must notify the contracting officer in writing. The same notification is required when the contractor believes total costs will significantly exceed or fall short of the original estimate.11Acquisition.GOV. FAR 52.232-20 – Limitation of Cost Missing that notification is one of the fastest ways to lose reimbursement eligibility for overruns, because no informal communication from anyone other than the contracting officer can change the ceiling.

What the Contractor Needs on Its Side

Winning a CPFF contract takes more than technical capability. The contractor’s accounting system has to pass review before the government will award a cost-reimbursement deal. It must segregate direct from indirect costs, accumulate direct costs by contract, and allocate indirect costs through a logical and consistent methodology. Auditors evaluate it against the Standard Form 1408 criteria during a pre-award survey, and the system must give reasonable assurance that cost data is reliable, mischarges are minimized, and contract charges are consistent with billing procedures.12Defense Contract Audit Agency. Accounting System Requirements and Pre-Award Audits A contractor with an inadequate accounting system will not receive a cost-reimbursement award. For small businesses breaking into government work, this is usually the hardest prerequisite to clear.

Every dollar claimed also needs a paper trail: timekeeping records, purchase orders, receipts, subcontractor invoices, and documentation behind indirect cost allocations. On defense contracts, the Defense Contract Audit Agency examines incurred cost submissions, progress payments, and related items.13Defense Contract Audit Agency. DCAA Contract Audit Manual Chapter 14 – Other Contract Audit Assignments Civilian agencies run oversight through their own contracting officers and inspectors general, but the allowability, reasonableness, and allocability standards are the same across the government.

Records must be retained for at least three years after final payment on the contract, and a specific contract clause can require longer.14Acquisition.GOV. FAR Subpart 4.7 – Contractor Records Retention Destroying records early, even accidentally, can leave a contractor unable to defend costs during a final audit and result in disallowed charges long after the work is done.