A DSA project lookup is done through eTracker, a free online tool from California’s Division of the State Architect that shows the plan review and construction status of public school and essential services building projects. You can reach it at apps2.dgs.ca.gov/DSA/Tracker/. To pull up a record you need either the DSA application number or the county, school district, and school name.1California Department of General Services. Track Plan Review Process for School, Essential Services Construction Projects The tool covers active projects and older archived records.
What You Need Before You Search
The fastest route is the DSA application number. It has two parts: a two-digit regional office code, then a six-digit project number assigned sequentially by that office.2Division of the State Architect. Plan Review for Schools, Essential Services Construction Projects The regional office codes are:
- 01: Oakland
- 02: Sacramento
- 03: Los Angeles
- 04: San Diego
An application number like 02-100627 was the 627th project submitted to the Sacramento office.2Division of the State Architect. Plan Review for Schools, Essential Services Construction Projects You’ll often find the number on architectural blueprints, in school board minutes about facility work, or on building permits and notices of completion posted at the site.
Without the number, search by county, school district name, and school name.1California Department of General Services. Track Plan Review Process for School, Essential Services Construction Projects Spell them exactly as they appear in official records. A single campus can carry several projects at different stages, so the more specific you are, the less filtering you’ll do afterward.
Running the Search in eTracker
Start from the DSA project tracking page on the Department of General Services website, which links to the eTracker application.2Division of the State Architect. Plan Review for Schools, Essential Services Construction Projects If you have the application number, enter it directly to open a single project record. If you don’t, the path depends on the school type:
- For K–12 schools, choose the option to search school projects by county and school district. Pick the county from the map or list, then the district. Every project associated with that district’s schools will appear.
- For community colleges, use the separate community college search and browse projects by college.
Click any application number in the results to open the full record, which shows milestones, review history, and current status.3California Department of General Services. How to Look Up a Project in DSA Project Status
Older Projects
Projects submitted before eTracker existed carry four- or five-digit application numbers instead of the current six-digit format. To find them, click the Pre-Tracker link inside eTracker, select the Pre-Tracker Client List, and search by district name.3California Department of General Services. How to Look Up a Project in DSA Project Status These older records stay publicly accessible, which matters because school buildings often remain in use for decades and their original certification status is still relevant for renovations and insurance.
Reading the Project Status
Every project record shows a status that tracks where it sits in DSA’s pipeline: plan review, active construction, then either certification or closure without it.
During plan review, DSA staff evaluate blueprints for compliance with the California Building Standards Code (Title 24), covering structural, fire and life safety, and accessibility requirements. Review begins within five working days of a registered submittal.4Division of the State Architect. Start Construction Project by Submitting Plans for Review Once plans are approved, construction proceeds under a certified project inspector, who verifies that the work matches the DSA-approved plans and meets code.5Division of the State Architect. Project Inspector Certification
The status most people are actually looking for is certification. A certified project has a DSA letter confirming that construction was completed in accordance with all applicable safety requirements.6California Department of General Services. Project Certification for Schools, Essential Services Construction Projects If you are a parent, community member, or board member asking whether a building went through the full safety process, that letter is the answer.
Certification is not automatic when construction ends. DSA reviews the file to confirm the required paperwork was submitted and outstanding issues resolved.7Division of the State Architect. Project Certification Guide If documents are missing, DSA sends a 90-day letter to the architect and district requesting everything within that window.6California Department of General Services. Project Certification for Schools, Essential Services Construction Projects
When a Record Says “Closed Without Certification”
This is the status that should get your attention. DSA closes a project without certification when it cannot verify that construction was completed to code. That happens either because deviations from the approved plans were reported during construction, or because required verification documents never came in within the 90-day deadline.6California Department of General Services. Project Certification for Schools, Essential Services Construction Projects
The consequences carry weight. DSA will not approve new proposed projects associated with uncertified construction, so a district can find itself blocked from other campus improvements until the outstanding project is resolved. If a building becomes occupied without certification, DSA places a report on the deficient paperwork in the Certification Box, which is open to the public.6California Department of General Services. Project Certification for Schools, Essential Services Construction Projects California law does not prohibit a district from occupying a building before certification is issued, but doing so without completing the process creates a public record of non-compliance and blocks future approvals.
Partial certification is possible. DSA can certify portions of a project’s scope separately if those portions include everything needed to make the affected structures fully code-compliant, including accessibility and fire safety.6California Department of General Services. Project Certification for Schools, Essential Services Construction Projects That helps districts that completed most of the work properly but had a problem with a specific component.
If the Lookup Doesn’t Answer Your Question
DSA runs four regional offices, and each handles projects submitted from its geographic area. The regional code in the application number tells you which office to call; a number starting with 03, for example, went through Los Angeles.2Division of the State Architect. Plan Review for Schools, Essential Services Construction Projects
- Oakland (01): 1515 Clay Street, Suite 1201, Oakland, CA 94612, (510) 622-3101
- Sacramento (02): 1102 Q Street, Suite 5200, Sacramento, CA 95811, (916) 445-8730
- Los Angeles (03): 355 South Grand Avenue, Suite 2100, Los Angeles, CA 90071, (213) 897-3995
- San Diego (04): 10920 Via Frontera, Suite 300, San Diego, CA 92127, (858) 674-5400
DSA headquarters in Sacramento takes general inquiries at (916) 322-2490.8Division of the State Architect. Contact Us