How to Fill Out a Contractor’s Affidavit Step by Step

To fill out a contractor’s affidavit, you list every subcontractor and supplier on the project with what they were owed and what they’ve been paid, declare any unpaid balances as exceptions rather than omitting them, and sign the completed form in front of a notary before submitting it with your final payment application. The form is sworn under oath, so accuracy is not a formatting concern but a legal one.

Confirm Which Form You’re Using

Before you fill anything in, make sure you have the right document. The most widely used version is AIA Document G706, “Contractor’s Affidavit of Payment of Debts and Claims.” If your contract references AIA documents, this is almost certainly what the owner or architect expects.

A companion form, AIA Document G706A (“Contractor’s Affidavit of Release of Liens”), is sometimes required alongside G706. G706 is the affidavit itself, where you swear that project debts have been paid or list the exceptions. G706A adds a sworn confirmation that you’ve collected lien waivers from everyone in the payment chain, with the actual waivers attached.1AIA Contracts. Instructions: G706A-1994, Contractor’s Affidavit of Release of Liens Submitting G706 alone won’t satisfy a requirement for G706A.

Some owners, lenders, or title companies use their own proprietary affidavit forms, and a few jurisdictions have statutory forms that must be used for the affidavit to carry legal weight. Check your contract and confirm the form before you start. Using the wrong one can delay final payment by weeks.

Gather Your Records First

Completing the affidavit goes quickly if your paperwork is organized. It becomes a scramble if you’re chasing invoice totals and subcontractor addresses at the last minute. Pull the following together before you sit down with the form:

  • Project identification: project name, site address, owner’s full legal name and address, architect’s name if applicable, and the architect’s project number. On AIA G706, the “Contract For” field refers to the scope of your contract (such as “General Construction” or “Mechanical Work”), not the project name.2AIA Contracts. Instructions: G706-1994, Contractor’s Affidavit of Payment of Debts and Claims
  • Contract financials: the original contract amount, every approved change order with its dollar value, and the adjusted contract sum. A missing change order here creates a discrepancy the owner or lender will catch.
  • Subcontractor and supplier list: full legal name, address, and contact information for every subcontractor, material supplier, and equipment vendor who worked on or supplied the project.
  • Payment records: for each party, the total contract or purchase order amount, amount paid to date, and any remaining balance. These need to match your accounting records exactly.
  • Lien waivers: if G706A or a similar release affidavit is required, the actual signed waivers from each subcontractor and supplier.
  • Supporting documentation: invoices, receipts, and payment confirmations that back up your numbers. You won’t attach all of them, but you need them available if anything gets questioned.

Filling In the Form

The exact layout varies by form, but the logic is the same whether you’re using AIA G706, a lender’s proprietary version, or a jurisdiction-specific template. Work through it in order rather than jumping around.

Project and Party Information

Start at the top with the identifying details: project name, site address, contract date, and the names and addresses of the owner and your company. On AIA G706, also fill in the architect’s project number and the “Contract For” scope description. Names should match the contract exactly. A mismatch between your affidavit and the contract creates ambiguity that a title company will flag.

One field that regularly trips people up: the state and county at the top of AIA G706 refer to where the notarization takes place, not the project location.2AIA Contracts. Instructions: G706-1994, Contractor’s Affidavit of Payment of Debts and Claims If your project is in one county but you’re getting notarized in another, use the notary’s county.

Contract Sum and Change Orders

Enter the total contract amount, including all approved change orders. The adjusted sum should match the most recent application for payment. If those numbers don’t line up, stop and reconcile them before going further.

Subcontractor and Supplier Listing

List every subcontractor and supplier with their contract amounts, payments made, and outstanding balances. This is where most errors happen. Contractors forget lower-tier suppliers they paid directly, overlook a small rental company, or transpose digits from their accounting software. Go through your job cost report line by line. If someone provided labor or materials on this project, they belong on the list regardless of how small the amount.

Exceptions

The affidavit isn’t a promise that every penny is settled. It’s a truthful accounting of where things stand. If every party has been paid in full, indicate that no exceptions exist. On AIA G706, you enter “None” in the exceptions space.2AIA Contracts. Instructions: G706-1994, Contractor’s Affidavit of Payment of Debts and Claims

If any balances remain, list each one as an exception with the party’s name and the amount still owed. When exceptions are listed, the owner has the right to require you to furnish a lien bond or indemnity bond covering each one before releasing payment.2AIA Contracts. Instructions: G706-1994, Contractor’s Affidavit of Payment of Debts and Claims Being upfront about unpaid balances is far better than omitting them. An omission turns an honest debt into potential fraud.

A Final Review Before You Sign

Compare every figure against your payment records. Verify that subcontractor names and addresses are legal names, not trade names or abbreviations. Confirm the adjusted contract sum accounts for all change orders. If the project had retainage, make sure the numbers reflect whether retainage has been released. This is your last chance to catch a mistake that could delay payment or expose you to liability.

Notarizing and Submitting

A contractor’s affidavit is a sworn statement, so the signature typically has to happen in front of a notary public. The notary confirms your identity, administers the oath, watches you sign, and applies the seal. AIA’s own instructions specify that the notary should administer a sworn oath referencing the written statements on the form before signing and sealing.2AIA Contracts. Instructions: G706-1994, Contractor’s Affidavit of Payment of Debts and Claims The notary is not verifying that your numbers are correct; that responsibility stays with you.

Bring valid government-issued identification. Do not sign the form before you arrive. Notaries need to witness the actual signing, and a pre-signed document will be rejected.

Once notarized, submit the completed affidavit to whoever your contract designates, usually the owner, the architect, or the lender. Under AIA A201, the affidavit goes to the architect with your final payment application, and final payment does not become due until the contractor submits an affidavit stating that all payrolls, material bills, equipment costs, and other project-related debts have been paid or otherwise resolved.3AIA. AIA Document A201-2017 If G706A is required, submit both forms together with the lien waivers attached. Keep a copy of everything you submit.

What Errors Cost You

The most immediate consequence of an affidavit with mistakes or missing information is that the owner withholds final payment. Under standard contract language, the owner is not required to pay until the affidavit is complete and acceptable.3AIA. AIA Document A201-2017 Correcting and resubmitting takes time, and your cash flow takes the hit in the meantime.

Because you’re signing under oath, deliberately false statements constitute perjury. Under federal law, perjury carries a potential sentence of up to five years in prison and a fine of up to $250,000.4Congress.gov. False Statements and Perjury: An Overview of Federal Criminal Law State perjury statutes vary but generally treat it as a felony. Perjury requires a knowing falsehood, so a genuine mathematical error won’t land you in prison. Listing a subcontractor as “paid in full” when you know they’re still owed $40,000 is the kind of intentional misrepresentation that triggers criminal exposure.

A false affidavit also opens the door to civil fraud claims. If an owner or lender relied on your sworn statement and later got hit with a mechanic’s lien from an unpaid sub, they can sue you for the resulting damages. Officers and principals who personally sign a false affidavit can face individual liability even when signing on behalf of the business, and fraud-based debts survive bankruptcy.

Records to Keep After Submission

Once the affidavit is submitted and final payment is released, keep copies of the notarized affidavit, all attached lien waivers, subcontractor payment records, invoices, and correspondence related to the final payment process. Disputes sometimes surface months or even years after project completion. Many construction contracts and government regulations require retention periods of three to five years after final payment, and keeping everything for at least six years covers most statutes of limitation for breach of contract and fraud claims in most jurisdictions.

Store digital copies alongside originals. If a subcontractor claims two years from now that they were never paid, the payment confirmations and their signed lien waiver are the documents that settle the argument.