To fill out a subcontractor payment form (AIA G702), you enter your original contract sum, add net approved change orders, pull the total completed and stored figure from your G703 continuation sheet, subtract retainage and prior payments, and the remainder on Line 8 is what you’re requesting this period. The form itself is only a one-page summary; the accuracy lives on the G703 behind it and in the supporting documents you attach. Get the arithmetic to tie out, match the retainage percentage in your subcontract exactly, and submit before the monthly cutoff, and a properly certified application moves to payment on the schedule your contract sets.
Before you start, confirm the G702 is actually the form your subcontract calls for. On projects using the ConsensusDocs family, you may be required to submit ConsensusDocs 710 instead, which asks for the same financial data but requires a notarized certification.1ConsensusDocs. Payment Application – 710 Federal contracts where progress payments are based on costs incurred use Standard Form 1443 with different reporting rules entirely.2General Services Administration. Contractor’s Request for Progress Payment (Standard Form 1443) Submitting the wrong form is an automatic rejection. A single-use digital license for the G702 runs roughly $50 to $60 through AIA’s contract documents site.3AIA Contracts. G702-1992 Application and Certificate for Payment
Set Up Your Schedule of Values First
You can’t complete a G702 without an approved schedule of values, because every row on the G703 continuation sheet comes from it. The schedule assigns a dollar amount to each discrete task in your scope, and the totals of all line items must equal your original contract sum exactly.
Break the work into pieces the GC or architect can actually verify in the field. “Rough-in electrical, Building A, floors 1–3” is a usable line item; a single lump sum for all electrical work is not. Include both labor and material in each line item unless your contract requires them separated.
Most GCs review a preliminary draft, sometimes called a pencil draft, before formally accepting the schedule. If they think a line item is front-loaded — meaning you’ve weighted early tasks to accelerate cash flow — they’ll flag it or reject the schedule outright. Undervaluing early work has the opposite problem: you end up financing materials out of pocket longer than necessary. Values should reflect the real cost of each task.
The G702 Line by Line
The header of the form asks for the project name, the application number (start at 001 for your first billing period and increment each cycle), and the period-to date, which is the last day of the cycle you’re billing for.4Connecticut Department of Administrative Services. AIA Document G702 – 1992 Application and Certificate for Payment Below the header, nine numbered lines carry the math.
- Line 1, Original Contract Sum. The amount in your executed subcontract. This number never changes over the life of the project, no matter how many change orders follow.
- Line 2, Net Change by Change Orders. The positive or negative total of all approved change orders to date. Only executed changes belong here. Billing for unapproved extras is one of the fastest ways to get an application bounced.
- Line 3, Contract Sum to Date. Line 1 plus Line 2. The current total value of your subcontract.
- Line 4, Total Completed and Stored to Date. Pull this directly from the grand total on your G703 (Column G). It captures the value of all work in place plus materials stored on site or at approved off-site locations.
- Line 5, Retainage. Line 5a applies the retainage percentage to completed work; Line 5b applies it to stored materials. Add them for total retainage.4Connecticut Department of Administrative Services. AIA Document G702 – 1992 Application and Certificate for Payment
- Line 6, Total Earned Less Retainage. Line 4 minus Line 5.
- Line 7, Less Previous Certificates for Payment. The total of all payments already certified on prior applications. Zero on your first application. On every application after that, it equals Line 6 from the prior certified application.
- Line 8, Current Payment Due. Line 6 minus Line 7. The amount you’re actually requesting this cycle.
- Line 9, Balance to Finish Including Retainage. Line 3 minus Line 6. Shows what remains on your subcontract.
The G703 Continuation Sheet
The G703 is where the real accuracy lives, because it feeds Line 4 and Line 5 on the G702. Each row corresponds to one line item on your schedule of values. For each row, you fill in three current-period figures:
- Column D: value of work completed in prior applications.
- Column E: value of work completed this period.
- Column F: materials presently stored, not yet installed.
Column G totals D, E, and F. Divide Column G by the scheduled value for that line and you get the percent complete, which is the number the architect will check against field conditions. The grand total of Column G is what you carry up to Line 4 of the G702; if those two numbers don’t match, the whole application will bounce back before anyone even looks at the field.
Getting Retainage Right
Retainage is the portion of each payment the GC withholds as a financial guarantee that you’ll finish. Your subcontract sets the percentage, and it typically falls between five and ten percent of each progress payment. Some states cap retainage by statute; California, for example, lowered its private-project cap to five percent effective January 1, 2026.
The percentage you enter on the G702 must match your subcontract exactly. If your contract calls for five percent on completed work and zero on stored materials, entering a blanket five percent across both categories creates a discrepancy that slows the review. Some contracts also reduce retainage after the project reaches fifty percent completion or after the architect certifies substantial completion, so watch for that language and adjust your application when the trigger hits.
Accumulated retainage is released near the end of the project, typically after substantial completion, in a separate or final application. That release requires an unconditional lien waiver rather than the conditional waivers used for progress payments.
Documents to Attach
The G702 and G703 are the cover; most GCs will not route your application for approval without a supporting packet. Missing documents are the most common cause of kickbacks.
Lien Waivers
A conditional lien waiver states that you release your right to file a mechanic’s lien for the amount being paid, once payment actually clears. It only takes effect when you receive the money.5Contractors State License Board. Conditional and Unconditional Waiver and Release Forms You also need conditional waivers from any lower-tier subcontractors or suppliers you’ve hired. Several states mandate statutory forms with specific language, so use the form required in the project’s jurisdiction rather than a generic template.
Insurance Certificate
A current ACORD 25 certificate of liability insurance showing your coverage limits, policy number, named insured, and expiration date. If the certificate on file has lapsed or is about to, get a fresh one from your insurer before you submit.
Certified Payroll
Publicly funded work — federal, state, or local — typically requires certified payroll records proving prevailing wages were paid. Federal projects trigger this under the Davis-Bacon Act. States have their own prevailing wage laws, and electronic submission is increasingly the norm.
Stored-Materials Documentation and Progress Photos
For anything you’re billing in Column F, include vendor invoices, delivery receipts, and photographs showing the materials on site or at the approved storage location. Some contracts also require proof of insurance covering stored materials against theft or damage. For completed work, date-stamped photos matched to your G703 line items give the reviewer a quick way to confirm claimed percentages.
Mistakes That Get Applications Rejected
The same errors surface month after month. Any one of them will cost you a billing cycle.
- Math that doesn’t tie out. The grand total on the G703 must equal Line 4 on the G702. Retainage must match the contract percentage applied to the correct subtotals. If a reviewer has to reach for a calculator to reconcile your numbers, expect a rejection rather than a correction.
- Overbilling. Claiming sixty percent complete on a line item an inspector can see is closer to forty is the fastest way to lose credibility. Once a GC catches overbilling, every future application gets tougher scrutiny.
- Billing unapproved change orders. Extra work performed without an executed change order does not belong on the application. Get the change order approved, then bill it the following month.
- Stale or wrong supporting documents. A conditional waiver for the wrong period, an expired insurance certificate, or a missing certified payroll report will stall the whole application.
- Missing the deadline. Most contracts set a monthly cutoff. Miss it by a day and your payment slides to the next cycle, which on Net 30 terms can push money out an additional 60 days.
How to Submit
Your subcontract tells you where and how, and following those instructions exactly matters more than it seems. Commercial projects increasingly use construction management platforms such as Procore or Textura, which timestamp your upload and route the application through the GC’s approval workflow. These portals typically want a single merged PDF of everything — G702, G703, waivers, insurance certificate, and any other attachments — uploaded before the portal’s cutoff time.
If the contract calls for hard copies, use a method that creates a receipt: certified mail with return receipt requested, or hand delivery with a signed acknowledgment. Email submissions are common on smaller projects; follow any subject-line or file-naming conventions the contract specifies. However you submit, keep a copy of the full packet and a record of the exact date and time it went out. That paper trail becomes critical if a payment dispute develops.
What Happens After You Submit
The GC or the project architect reviews the application against field conditions, checking whether the percentages you claimed on the G703 match what they see on site. This often includes a site walk, particularly for large dollar amounts or line items nearing completion.
If a reviewer finds a discrepancy — say you claimed a line at seventy percent but the work looks closer to fifty-five — they will either reject the application for revision or adjust the disputed line and certify the rest. That negotiation is sometimes called a pencil draw. When part of the application is disputed, the GC should release funds for the undisputed portion rather than holding the entire payment.
On federal construction contracts, a proper payment request is due within 14 days of receipt by the contracting officer.6Acquisition.GOV. Subpart 32.9 – Prompt Payment If the agency pays late, it owes interest at the Prompt Payment rate, currently 4.125 percent for the first half of 2026.7Bureau of the Fiscal Service. Prompt Payment Private work has no single federal standard, but most states have prompt-payment statutes requiring GCs to pay subcontractors within a set window, commonly seven to thirty days after the GC receives payment from the owner.
Private-project payment terms typically run Net 30 or Net 45. Between the monthly cutoff, the review period, and the payment terms, you can wait 45 to 75 days from doing the work to seeing the money in your account. Plan cash flow around that reality from your first application forward.